U.S. data center construction costs rise 13% on AI demand
Turner & Townsend reports costs are triple the ten-year average, driven by labor shortages and power connection delays that now stretch into years.
By Alessia Desai ·

Building a data center in the United States cost 13% more this year than it did last year, according to a report released by Turner & Townsend on Thursday. The firm, a global project management company, found that this rate of increase is more than double the global average. It is also approximately three times higher than the industry's ten-year average.
The analysis reviewed more than 500 live or recently completed projects across 62 markets. The study also included survey data from 400 experts working in the data center industry. Paul Barry, the firm's North America data center lead, said tighter schedules have forced contractors to add larger risk allowances to their pricing. These allowances cover acceleration costs, overtime, and incentives to attract labor. Companies are also charging higher fees to manage the risk of delivering projects faster than traditional standards.
Power availability remains a major obstacle. Globally, 56% of surveyed respondents identified power as a primary barrier to project delivery. Just over half of these experts reported that utility connections typically take between one and two years to complete. Almost a third said the process can take more than two years. The cost of power also varies by region. For a typical 60-megawatt design, prices range from $15.01 per watt in Silicon Valley to $10.51 per watt in Dallas.
Labor shortages are adding pressure to U.S. construction projects. Only just over one quarter of survey respondents stated that their contractor capacity was sufficient to manage current backlogs. This scarcity of skilled labor complicates the ability to meet aggressive delivery schedules. A recent report from PwC projects that global capital expenditure on data centers will grow from approximately $800 billion this year to $1.8 trillion annually by 2050. The United States is expected to secure nearly half of all global investment in AI infrastructure, a category that includes both data centers and chips.
Barry anticipates that cost increases will moderate somewhat in the coming year, with projections ranging between 6% and 10%. Many major projects have already begun or are currently starting, meaning much of the cost risk has already been factored into their contracts. Barry noted that 2026 has marked a surge in the procurement of large projects. If demand continues at its current level, a steady flow of new project starts is expected.